List of the potential threats:
|
Fire Alarms (check regularly for batteries)- $100 Extinguishes (check yearly if its in working condition) - $100 Evacuation procedure Fire proof building
|
Have a plan for a secondary building, into which you can move temporary.
Have a spare laptop or PC off site with all the needed application to temporary use for the business. |
|
|
Have a good water system Water pump - $1000 |
Have a plan for a secondary building, into which you can move temporary.
Have a waterproof electricity system. |
|
|
Tornado/Earthquake |
Tornado/Earthquake proof office.
|
Have a plan to restore office equipment as soon as possible. |
|
Theft |
Have a security system installed properly – $2000.
Store all vulnerable data in secure servers - $2500. |
Have a plan to restore office equipment as soon as possible. |
|
Virus/Spy-ware |
Have latest security software: anti-virus, anti-spy software, firewall - $200 to $400 every year.
Store all vulnerable data in secure servers - $2500.
Have back up of all data on regular basis - $500 (plus additional cost for the back up media) |
Have all the data back-up plus have a ghost image of all the system for faster recovery. |
|
System failed |
Keep all system in air condition room. Regularly check and update all the system. Keep operation system in good condition. |
Have a stack of hardware to replace in case something failed. Have all the software ready for the reinstallation. |
|
Terrorist Act |
Have a security patrolling the office grounds. Have a good security system installed. Report all suspicious activities to the security officers. |
|
Detailed set of procedures for preventing and recovering
|
Disaster |
Resources |
Recovery |
Cost/Time |
|
Fire, Flood, Tornado/Earthquake |
|
|
|
Theft |
|
|
|
|
Virus/Spy-ware |
|
|
|
|
System failed |
|
|
|
Testing of the Sand Auto War will occur in the series of rounds. First round is when testers will start on testing of the software. When testing is finish or any of exit exiting criteria is met, all documented defects will be submitted to the development team for the fixing. After testing team will receive new version of the software new round of testing will occur. At this point all the technical documents and testing plan changes have to be made. New test round is setup and performed again. Same steps if followed until no errors found, development team or the project manager says that testing is complete.
Below is an example of the one round of the testing process.
o Black box testing technique will be used.
o Start of the testing – tester will start testing each form one by one.
o All the defects have to be documented.
o All documents submitted to the Tester Team Leader.
o At this stage testing might stop if any exiting criteria are met.
o Tester Team Leader submits documented defects to the development team for the correction purposes.
o After receiving new version of the program new round of testing will start.
o Continue until of the exit criterion met.
|
Name |
Role |
Responsibility |
Position |
|
Daniel Golitsyuski |
Tester Team Leader |
§ Testing of the forms. § Documentation of the testing. § Communication with management and development team. § Changes in Test Plan. § Management of the testing process. |
Full-time |
|
N/A (will be hired closer to testing period) |
Tester |
§ Testing of the forms. § Documentation of the testing. |
Casual |
|
Michael Chivers |
Tester Analyst |
§ Testing of the forms. § Documentation of the testing. § Changes in Test Plan. § Make sure all the testing done with company standards. § Coordinate QA activities for assigned projects. § Develop any scripts or new documentation for the testing. |
Full-time |
There will be no day-to-day schedule for the testing, for the reason that testing forms and material will be changed depending on the occurred errors. Each new day or round of testing Tester Team Leader with help of the development team leader will analyse what have to be tested first, which errors are most critical and develop rough plan test for the upcoming day or round.
Testers and development team possibly will have to work over time to meet the test schedule.
All the testing will start when developing team will submit first version of the SAW. Testing team will be given a week to complete the test of the game. If testing is not complete in given time, it will be stoped nevertheless.
At the end of every day all defect logs and reports will be submitted to the Tester Team Leader for evaluation. He will created plan for next day of testing and by communication with development team, analyse what have to be tested next.
At the end of the last day of the week of testing all the reports and logs have to be documented and submitted to the project manager.
o Testing cannot continue past submission date.
o Testing cannot continue if exit criteria are met.
Bug reporting and tracking will consist of following:
When new bug is found it will be documented in the defect log. There will be one defect log for each bug or error. Tester will use multiple defect logs to document all found bugs. Then this defect log will be given to the development team to work on it. After error is fixed, developer fills the result sheet where he specified what have been done to fix each error. Then result sheet goes to the Tester Team Leader, who will analyse it and make sure that everything is correct. By doing so, he can make sure that there no misunderstanding between developer and tester. For example if error wasn’t error at all or by some means should be overseen. Tester Team Leader will know about it and will inform all the team members or when tester think that this error should be fixed, Tester Team Leader can communicate with developer to resolve the conflict. After each round of testing tester fill the Test log where he documents everything what happed during the round of testing and Tester Team Leader will make sure that every bug recorded is fixed or at least have been review by the development team. Test log then will be submitted to the project management for further analyses and testing control.
Hence Tester Team Leader will be one responsible to make sure that all defect logs and result sheet is filled correctly. Test log will contain all the information collected from defect log and result sheet. This way it will be easily seen what have been fixed and what have been missed.
At the end of each week Tester Team Leader will communicate with developers to gather information on what has been fixed and what will be fixed soon. This way no conflict will occur between test team and development team.
|
Bug Log – Developers
|
|||
|
Problem Name: |
|
ID: |
|
|
Description: |
|
||
|
Developer Name |
|
Priority: |
1.High |
|
2.Moderate |
|||
|
Date: |
|
3.Medium |
|
|
4.Low |
|||
|
Further Action |
|
||
|
|
Developer Signature: |
||
|
Bug Log – Tester
|
|||
|
Problem Name: |
|
ID: |
|
|
Steps to Problem: |
|
||
|
Error message: |
|
Priority: |
1.High |
|
2.Moderate |
|||
|
Date: |
|
3.Medium |
|
|
4.Low |
|||
|
Assigned To: |
|
||
|
Fixed: |
Yes: |
No: |
|
|
Follow On: |
|
||
|
|
Developer Signature:_________________________ |
||
|
Maintenance Log
|
||
|
Version Number: |
|
ID: |
|
Description: |
|
|
|
Name of the class/file/function:
|
|
|
|
Assigned To: |
|
|
|
Date: |
|
|
|
Additional Notes: |
|
|
|
|
Developer Signature:_________________________ |
|
There are no comments on this page. [Add comment]